Oracle sends force majeure notice on its New Mexico Stargate data center

TechCrunch AI News

Summary

Oracle has issued a force majeure notice for its New Mexico Stargate data center, citing potential delays due to energy supply issues, though the company maintains the project is on schedule.

The notice would allow Oracle to delay payments should the facility miss its 2028 target to come online.
Original Article
View Cached Full Text

Cached at: 09/24/26, 07:05 PM

# Oracle sends force majeure notice on its New Mexico Stargate data center | TechCrunch Source: [https://techcrunch.com/2026/09/24/oracle-sends-force-majeure-notice-on-its-new-mexico-stargate-data-center/](https://techcrunch.com/2026/09/24/oracle-sends-force-majeure-notice-on-its-new-mexico-stargate-data-center/) Oracle has sent a force majeure notice to the developer of Project Jupiter, a Stargate data center campus in New Mexico,[Bloomberg first reported](https://www.bloomberg.com/news/articles/2026-09-24/oracle-cites-force-majeure-to-shield-itself-on-controversial-data-center)Thursday\. Force majeure clauses, common in energy and commodities contracts, excuse a party from contractual obligations when events outside its control get in the way\. Oracle is not seeking to exit as the campus’s main tenant, according to Bloomberg’s sources\. Instead, the notice would allow the company to delay payments should the facility miss its 2028 target to come online\. The notice also comes as AI data center construction faces growing scrutiny nationally, and as developers take on steep costs to build capacity for customers like OpenAI\. Oracle maintains that it does not expect a delay\. “Project Jupiter remains on our planned schedule,” Oracle said in a[statement to CNBC](https://www.cnbc.com/2026/09/24/oracle-data-center-force-majeure.html)\. “We are fully committed to New Mexico and confident in our path forward\.” Blue Owl Capital, whose unit received the notice, said in its own statement to CNBC that “this notice does not change the financial commitments to this multi\-year project\.” Neither Oracle nor Blue Owl immediately responded to TechCrunch’s requests for comment\. Still, the notice follows a string of setbacks at the site, many of them tied to its energy supply\. The campus, designed to handle 2\.45 gigawatts, is meant to run on gas\-powered fuel cells from Bloom Energy, which makes a reliable gas supply central to its timeline\. An Energy Transfer pipeline intended to deliver gas to the site has also been delayed nearly six months, to February 1, 2027, after regulators repeatedly denied permits for the line\. In August,[Bloomberg reported](https://www.bloomberg.com/news/articles/2026-08-18/oracle-openai-data-center-s-gas-pipeline-plan-rerouted-after-earlier-rejections)that the pipeline’s route had been changed following those rejections\. A separate air\-quality permit for the fuel cell system that would power the campus is also pending\. The state’s environment department faces a November 23 deadline to decide\. Project Jupiter is one of the flagship sites of Stargate, the AI infrastructure initiative Oracle, OpenAI, and SoftBank announced with President Donald Trump early in his second term\. The campus has drawn opposition from residents and environmental groups and has become a political flashpoint ahead of the midterm elections\. Oracle has responded with a public outreach campaign in the state aimed at winning over the project’s critics, according to Bloomberg\. *When you purchase through links in our articles,[we may earn a small commission](https://techcrunch.com/techcrunch-affiliate-monetization-standards/)\. This doesn’t affect our editorial independence\.* Aditya Mehta is a reporter at TechCrunch covering AI\. He’s supported by the Tarbell Center for AI Journalism and attended UC Berkeley\. You can contact from Aditya by emailing aditya\.mehta@techcrunch\.com or via encrypted message at adymehta\.74 on Signal\. [View Bio](https://techcrunch.com/author/aditya-mehta/)

Similar Articles

Stargate advances with 4.5 GW partnership with Oracle

OpenAI Blog

OpenAI and Oracle announced a partnership to develop 4.5 gigawatts of additional Stargate data center capacity in the U.S., bringing total Stargate infrastructure to over 5 gigawatts and supporting OpenAI's $500 billion investment commitment. The project is expected to create over 100,000 jobs and represents a major milestone in advancing U.S. AI infrastructure leadership.

OpenAI, Oracle, and SoftBank expand Stargate with five new AI datacenter sites

OpenAI Blog

OpenAI, Oracle, and SoftBank announced five new U.S. AI data center sites for the Stargate infrastructure project, bringing total planned capacity to nearly 7 gigawatts and over $400 billion in investment over three years. The expansion includes sites in Texas, New Mexico, Ohio, and Wisconsin, with plans to reach the original $500 billion, 10-gigawatt commitment by end of 2025.

Oracle fires 21,000 employees to fund AI spending

Hacker News Top

Oracle laid off 21,000 employees (13% of its workforce) to fund massive AI infrastructure spending, including a $300 billion contract with OpenAI, while facing regulatory hurdles and a credit downgrade that threatens a planned data center in Wisconsin.