13 years and $500 million for a stage adapter? Report justifies NASA cancellations.

Ars Technica News

Summary

A NASA inspector general report reveals that canceled Artemis programs, including a $500 million stage adapter, faced massive cost overruns and delays, justifying NASA's decision to streamline lunar exploration architecture.

<p>Three months ago, NASA Administrator Jared Isaacman announced the space agency was making a major pivot from building a space station in lunar orbit to a base on the surface. This "Ignition" event followed an earlier announcement in which NASA also said it was ending development of a new upper stage for its Space Launch System rocket.</p> <p>In the aftermath of these decisions, there was some grumbling—mostly from contractors involved with the programs—that NASA was foolishly walking away from nearly complete hardware that the space agency needed for its Artemis Program.</p> <p>Isaacman said these programs were not essential for landing humans on the Moon, and added that they had cost far more than originally budgeted and had been subjected to years of delays. Moreover, they were still not ready.</p><p><a href="https://arstechnica.com/space/2026/06/analysis-finds-the-exploration-programs-nasa-recently-canceled-were-running-way-late/">Read full article</a></p> <p><a href="https://arstechnica.com/space/2026/06/analysis-finds-the-exploration-programs-nasa-recently-canceled-were-running-way-late/#comments">Comments</a></p>
Original Article
View Cached Full Text

Cached at: 06/25/26, 05:14 AM

# 13 years and $500 million for a stage adapter? Report justifies NASA cancellations. Source: [https://arstechnica.com/space/2026/06/analysis-finds-the-exploration-programs-nasa-recently-canceled-were-running-way-late/](https://arstechnica.com/space/2026/06/analysis-finds-the-exploration-programs-nasa-recently-canceled-were-running-way-late/) In a written response to the report, the chief of NASA’s Human Spaceflight Directorate, Lori Glaze, said the data in the memorandum support NASA’s decision to cancel these programs earlier this year\. “NASA notes that the challenges summarized in the memorandum—cost growth, schedule slips, contractor performance issues, and evolving mission requirements—reinforce the rationale behind the decisions publicly announced during Ignition Day to streamline the Artemis architecture, modernize acquisition practices, and align programs with the nation’s objectives for sustained lunar presence,” Glaze wrote\. ## That’s an expensive stage adapter you’ve got there The least expensive of the four contracts, for the Universal Stage Adapter, is perhaps the most illustrative\. NASA contracted with Dynetics in June 2017 to design, test, and build this piece of spaceflight hardware\. Made largely of composites, the adapter weighed 9,650 pounds \(4\.3 metric tons\) and stood 33 feet \(10 meters\) tall\. The original contract awarded to Dynetics totaled $131 million, to which NASA later added $9 million for a payload separation system\. At the time the program was canceled earlier this year, the contract value had grown to $353 million, with a delivery date delayed to September 2028\. The inspector general’s report projected that the project would likely cost $497 million and not be ready until May 2030\. To be clear: NASA was likely going to pay half a billion dollars for a relatively straightforward stage adaptor\. This doesn’t have propulsion or anything like that on board\. Also, for some unfathomable reason, it was likely to take 13 years to build\. Another interesting note from the report is that the inspector general did not believe the Lunar Gateway, based on delays with the Habitation and Logistics Outpost, would have been operational until at least 2032\. Ars reported last week that[NASA formally asked](https://arstechnica.com/space/2026/06/nasas-1-1-billion-gateway-habitation-module-is-unlikely-to-be-used-for-something-else/)Northrop Grumman to stop work on this module\.

Similar Articles

Report: Kennedy Space Center not ready for era of super heavy rockets

Ars Technica

A NASA Office of Inspector General report warns that Kennedy Space Center's aging infrastructure cannot keep pace with the demands of super heavy rockets like SpaceX's Starship and Blue Origin's New Glenn, citing critical issues with nitrogen supply, power distribution, and road capacity.

One Mars spacecraft, two senators, and a cloud of questions

Ars Technica

NASA has released a solicitation for a $700 million Mars telecommunications orbiter, sparking controversy over eligibility requirements that appear to favor Rocket Lab, and raising questions about the future of the Mars Sample Return mission.